FG Re-opens Third Mainland Bridge Today



 The Federal Government announced yesterday that third Mainland Bridge would be re-opened today. The road was partially closed on July 7  to enable the contractor, Messrs Boroni Prono and Company Limited, to replace eight expansion joints on the bridge for a contract sum of N1bn. The re-opening was originally scheduled for November 6, but due to the fast pace of the repair works, the road would be delivered a week early.

 Those three  months were gruelling for motorists in Lagos state, what a huge relieve.